Lesson 04 of 10

Canteen

A canteen is sized by the meal schedule, the number of shifts, the kitchen process, and the flows of raw ingredients and prepared food, not just by the number of tables.

What you will be able to do after this lesson

You will be able to specify the canteen through the number of diners, shifts and the kitchen process specification.

Why it matters

The number of seats is derived from the number of diners and the number of meal sittings. A 70-seat canteen feeds a camp of 200 people in three sittings; with two sittings, more seats are needed. This is a decision for the client and the catering operator, not the module supplier.

The kitchen is a process facility: its equipment sets the electrical load, ventilation, water, sewerage with a grease trap and waste storage. That is why the kitchen process specification must be produced before the utility calculation for the whole camp, not after.

Staff, storage, preparation, dishwashing and dining areas are separated in the design in line with the sanitary requirements for catering facilities. In the spec this is a list of rooms and flows, not a single line reading "canteen".

Dining hall of a modular canteen
The number of seats follows from the number of diners and sittings; the services follow from the kitchen process

How to apply this on a project

  1. Step 1. Fix the number of diners and the number of sittings.
  2. Step 2. Obtain the process specification for the kitchen equipment.
  3. Step 3. Confirm the loads, ventilation, water, sewerage and waste storage.
  4. Step 4. Separate the staff, storage, preparation, dishwashing and dining areas in the design.

Typical mistake

Selecting the kitchen module after the electrical load and ventilation for the whole camp have been approved.

Check before the next step

  • Diners
  • Sittings
  • Seats
  • Equipment
  • Electrical load
  • Ventilation
  • Water and wastewater